The Health Ministry is defending delays in opening the new Weija-Gbawe Paediatric Hospital. The project is held up by a dispute with the World Bank. This dispute concerns alleged misprocurement. The World Bank is refusing to pay approximately GHS 14.8 million ($3.8 million).
Spokesperson Tony Goodman stated that the World Bank raised concerns about misprocurement. These concerns include allegations of inflated equipment prices. Some medical equipment was reportedly priced up to 11 times its market value. Mr. Goodman shared these details on the Asaase Breakfast Show on Wednesday, May 6. The hospital project began in 2023.
This development fits into a broader picture of Ghana's public finance management. Large infrastructure projects often rely on international partners like the World Bank. Transparency and proper procurement are critical. Previous reports have highlighted concerns about value for money in government contracts. The delay of this hospital, crucial for child healthcare, underscores these challenges.
Mr. Goodman explained that the World Bank insists what happened was misprocurement. He confirmed they will not pay the GHS 14.8 million. The government has considered covering some costs. However, contractual and financial arrangements with the World Bank limit this. Goodman said, "If they say they are not paying some amount and you go to pay, you will have issues."
The stalled commissioning means the facility, largely built, remains unused. This raises concerns about the deterioration of idle medical equipment. The contractor has refused formal handover until disputes are resolved. This is a standard procedure to clarify responsibility for any future issues. Multiple meetings are underway, including with World Bank officials currently in Ghana. Mr. Goodman expressed optimism that the facility would be used "in no time." A specific commissioning date was not provided. The ministry acknowledges the potential negative impact of prolonged delays on vital medical supplies.