976MVA Kumasi line upgrade brings a second three-day Ashanti power cut this month

Published
2 min read4 min listen

Parts of the Ashanti Region are without power from 7.30am to 5pm today, Sunday 22 November, and on Monday and Tuesday.

The Electricity Company of Ghana (ECG) said in a notice issued on Saturday that the cuts let the Ghana Grid Company (GRIDCo) continue upgrading the Anwomaso to Ridge Bulk Supply Point transmission line, Asaase Radio reported. Named areas include parts of Kaase, Guinness Ghana Limited, Fan Milk and Atonsu Kuwait.

This is the second three-day round on the line this month. ECG cut power to an overlapping list of areas, also from 7.30am to 5pm, from 16 to 18 November, Graphic Online and MyJoyOnline reported.

By StatsGH's count, the two rounds add up to 57 hours of scheduled cuts: six days of 9.5 hours each.

What is being built

GRIDCo is replacing a 364MVA single-circuit line with a 2 x 488MVA double circuit, 976MVA in total. That is 2.7 times the old rating, an increase of 612MVA or 168%.

Energy News Africa reported on 7 November that GRIDCo chief executive Frank Asirifi Otchere expected the line work to be finished by the end of November. "When it is completed, we are expecting to see increased capacity to serve demand in Kumasi," he said.

GRIDCo has also replaced a 66MVA transformer at the Ridge substation with a 145MVA unit, in service since June.

Anwomaso–Ridge line rating, MVA

New double circuit is 2 × 488MVA. Source: ECG notices via Asaase and Graphic.

Old single circuit
364
New double circuit
976

976MVA is 2.7 times the old 364MVA rating, an increase of 612MVA.

Why Anwomaso matters

Anwomaso is home to three gas-fired plants. The Energy Commission's Energy Outlook for Ghana 2026 (Table 2, installed generation capacity as of the end of 2025) lists Anwomaso Thermal at 250MW, AKSA Anwomaso at 205MW and CENIT Anwomaso at 110MW.

That is 565MW, or 13.5% of the table's 4,178MW of grid thermal capacity.

The 2027 Budget says the AKSA plant is "operating at 98 percent load without interruption". It says CENIT's plant, which it puts at 100MW, has been synchronised to the grid and commissioning "is being finalised".

The government plans to expand the AKSA plant from 205MW to 350MW in 2027 (paragraphs 1275 and 1276).

Only 36% of respondents to the KPMG/UNDP pre-budget survey called electricity supply very or mostly reliable, as we reported.

Limitations

Line ratings in MVA and plant capacity in MW are different measures, and Anwomaso power also leaves by other lines, so the figures cannot be compared directly. The end-November date is GRIDCo's target, not a confirmed completion.

No customer count or project cost has been published. We relied on outlet reports of ECG's notices, and did not obtain fresh comment from ECG or GRIDCo.

Sources: Asaase Radio, "Three-day planned blackout to hit parts of Ashanti from 22 to 24 November", 22 November 2026; Graphic Online, "Planned power outage in Ashanti as GRIDCo upgrades Anwomaso-Ridge transmission line from November 16", 14 November 2026; MyJoyOnline, "ECG announces three-day planned power outage in parts of Ashanti Region for upgrade works", 14 November 2026; Energy News Africa, "GRIDCo Assures Kumasi And Northern Ghana Of Improved Power Supply By December", 7 November 2026; Energy Commission, Energy Outlook for Ghana 2026, Table 2; Ministry of Finance, 2027 Budget Statement and Economic Policy, paras 1275–1276; StatsGH, KPMG/UNDP pre-budget survey, 11 November 2026.