Ghana seeks US grants and guarantees for its first nuclear plant ahead of a US$200m, 24-month readiness programme

Published
2 min read3 min listen
Photo: StatsGH chart

Ghana has identified possible US grants, project financing and investment guarantees for its first nuclear power plant, Deputy Minister for Energy and Green Transition Richard Gyan-Mensah said after a five-day working visit to the United States.

No funding package, guarantee or technology agreement has been announced.

The visit comes ahead of a US$200 million nuclear-readiness programme that the 2027 Budget sets to run for 24 months, from January 2027 to December 2028. Spread evenly, that is about US$8.3 million a month, by StatsGH's calculation.

What the US talks covered

Mr Gyan-Mensah led the delegation on behalf of the sector minister, John Abdulai Jinapor. It met US government agencies, the Nuclear Energy Institute, George Mason University and nuclear technology companies.

He said the talks identified "practical opportunities for US support, including grant-funded preparatory studies, project-development financing, investment guarantees, technical assistance and independent assessment of available nuclear technology options". Nuclear regulation, security, academic cooperation and training were also discussed.

What the US$200 million is meant to buy

The Budget's target is to complete readiness by December 2028 and sign an engineering, procurement, construction and financing contract for a fully state-owned nuclear baseload plant. It says plainly that readiness in 2028 does not mean nuclear power generation in 2028.

Readiness covers site studies, technology selection, environmental assessment, financing, licensing preparations, safeguards, emergency planning and the safety case. The government also plans to train more than 2,000 Ghanaian scientists for the programme.

Finance Minister Cassiel Ato Forson told Parliament on 12 November that the plant would remain a strategic national asset and would not be developed as an independent power producer. International partners would provide only technology, finance, engineering and specialist services.

Where the programme stands

Land acquisition for two candidate sites is under way, and a Bill to set up a Nuclear Power Corporation of Ghana has been submitted to Parliament. Nsuban in the Western Region is the preferred site, with Obotan in the Central Region as the alternative. Talks with international vendors to choose a technology are continuing.

Limitations

The Budget gives a single US$200 million figure with no breakdown by activity, year or funder, so it is not clear how much will come from the national budget and how much from partners. The monthly figure assumes even spending. The possible US support was described by the Deputy Minister; no US agency statement or signed agreement was available.

Official statements differ on when a plant could first produce power, and the Budget sets no generation date. The Ministry of Energy and Green Transition, Nuclear Power Ghana and the US Embassy in Accra were not asked to comment for this article.

Numbers behind the story +

Figures used

  • Nuclear-readiness programme: US$200 million (About US$8.3m a month if spent evenly over the programme)
  • Readiness programme length: 24 months (Aimed at a construction and financing contract, not power generation)