The World Bank has rated Ghana's Energy Sector Recovery Program "Unsatisfactory" on both progress towards its objective and overall implementation, down from "Moderately Satisfactory", in an implementation status report archived on 30 June 2026.
The report puts the combined financial losses of the Electricity Company of Ghana (ECG) and the Northern Electricity Distribution Company (NEDCo) at US$1.52 billion in May 2026, against a target of US$525 million by December 2027.
The downgrade was first reported in July by Africa Business Insight.
It returned to the news on Saturday 28 November, when Energy Ministry spokesman Richmond Rockson was asked about it on JoyNews' Newsfile, 3News and MyJoyOnline reported.
What the report says
Combined losses rose from US$1.11 billion at 30 September 2025 to US$1.52 billion at 18 May 2026, an increase of about 37%, and are 21% above the programme's December 2022 baseline of US$1.26 billion. To reach the US$525 million target they would have to fall by about 65%.
ECG accounts for US$1.46 billion of the May 2026 figure, up from US$1.05 billion, based on its 2025 financial statements published in May 2026. NEDCo's US$57.1 million comes from its 2024 statements, so the total is provisional.
The programme's target is US$525 million by December 2027. Source: World Bank implementation status report, P173258 (30 June 2026).
May 2026 total is provisional because NEDCo's financial statements had not been published.
Other indicators in the report:
- ECG's cash recovery index was 0.62 in May 2026, down from 0.64 in September 2025, against a target of 0.76.
- ECG's electricity losses were 26.88%, against a target of 19.20% and a baseline of 28.40%.
- ECG had installed none of the 1,050,000 smart meters targeted.
- ECG had introduced district-level energy accounting in 20% of districts. The target is 100% by 30 June 2026, which the report says is likely to be delayed.
- 38,000 people had been given clean cooking solutions, against a target of 457,000.
- GRIDCo had not yet prepared its security-constrained economic dispatch methodology or procured consultants, and the report rates that item off-track.
Why, according to the report
The report says timelines were affected by the elections and the change of administration, and that disbursement-linked results were delayed by "new procurement directives and disbursement caps". For a series of stalled indicators it cites "No Commitment Authorization from MoF to allow for disbursements needed to facilitate achievement of targets".
It expects delivery to speed up with "better coordination among implementing agencies and the Government on approvals processes".
The ministry's response
Mr Rockson said the Finance Minister held back commitment authorisations so that inherited loan facilities could be audited. MyJoyOnline quoted him saying the Finance Minister had noticed some energy-sector companies spending facilities on "other auxiliaries", such as vehicles, and that World Bank credits "are not free monies".
He said the government had since engaged the Bank and expected progress to show at the next assessment. StatsGH has not seen the audit, and these are the ministry's statements.
The report matters beyond the programme because it is the Bank's own scorecard for the distributor that the government now wants to open to private concessionaires, as the Energy Minister told Parliament on Friday.
Limitations
This is a World Bank staff assessment, with data to 18 May 2026, so it does not reflect anything since. The US$250 million size of the programme comes from 3News and is not stated in the report text StatsGH read.
ECG, the Ministry of Finance and the World Bank were not asked for comment. The percentage changes are StatsGH calculations from the report's figures.
Sources: