Energy Minister John Abdulai Jinapor has blamed extreme El Niño heat, a gas-infrastructure fault and a tree felled onto a transmission line for the power cuts of the past week, and said the Kumasi transmission works should finish on 10 or 11 December.
He insisted the country is not shedding load and that only a few pockets of outages remain, 3News reported from his remarks at Friday's Ghana Energy Awards.
On JoyNews' Newsfile on Saturday 28 November, ministry spokesman Richmond Rockson said the recent outages come from transmission and distribution bottlenecks rather than generation. "For the generation side, as I mentioned, we've largely dealt with the problem," he said, Adom Online reported.
He also conceded, in 3News's account, that "we're not out of the woods yet".
What the ministers say caused it
- Heat: Mr Rockson said the last four to eight weeks of El Niño heat had put pressure on distribution systems. He said about 2,000 transformers had been deployed this year.
- Gas fault: Mr Jinapor said backup pumps at the gas infrastructure failed and needed new parts. Reports did not name the plant or pipeline.
- Fallen tree: GRIDCo said illegal chainsaw operators felled a tree onto its 330kV Aboadze to Anwomaso line on 25 November. It said repairs were completed at about 12.07pm on 26 November, MyJoyOnline reported. This is a different line from the Anwomaso to Ridge upgrade.
- Overloaded lines: Mr Rockson said a Kumasi line installed about 20 years ago now serves a far larger population, and named Greater Accra hotspots: Dansoman, Adenta, Amrahia, Pokuase, Amasaman, Lakeside, New Legon, East Legon Hills and Oyarifa, 3News reported.
Kumasi: new finish date, different capacity claims
Mr Jinapor told Asempa FM that the Kumasi works would finish "by the 10th or 11th of December", Adom Online reported on 26 November. That is later than the end-of-November target GRIDCo's chief executive gave in early November.
StatsGH reported the first two rounds of cuts for the upgrade in its coverage of the 976MVA Anwomaso to Ridge line, and has added a third, six-day round to run to 1 December.
The ministers describe the capacity gain differently. Mr Jinapor said the new line has four times the capacity of the old one; Mr Rockson said capacity goes from "about 364" to "almost 1,000". The ratings in ECG's notices, 364MVA to 976MVA, give 2.7 times, by StatsGH's calculation, which fits Mr Rockson's description rather than the four-times claim.
The dispute over transmission investment
Energy analyst Kwadwo Poku has said cancelled KfW financing for an Accra to Kumasi transmission line means the power problems could last two years, as StatsGH reported on Saturday. Mr Rockson rejected the claim that no transmission contracts had been awarded in two years, citing an October 2026 161kV project, the Eastern Corridor and evacuation works for a 1,450MW plant.
He said the government had "practically no reserve margin" when it took over and was shedding 700MW in December 2024. StatsGH has not seen the contracts or the KfW agreement.
Still to come this weekend
ECG has scheduled more planned cuts: eight hours from 9am to 5pm on Sunday 29 November in Sekondi-Takoradi and 21 areas fed from the Asawinso substation, including Bibiani and Chirano; and Eastern Region cuts on Monday 30 November (Akwatia, Kade) and Tuesday 1 December (Adweso, Bonya), 3News reported.
Limitations
These are the ministers' own explanations as reported by 3News, Adom Online and MyJoyOnline. StatsGH has not seen ECG or GRIDCo outage logs or the commissioned grid audit, and neither the Ministry nor GRIDCo was asked for further comment.